Work stopped at Tarali: forest range officer says the wildlife board never cleared it

The Maharashtra forest department has ordered all work on the 1,500 MW Tarali pumped storage project in Patan taluka of Satara district to stop, saying it began without prior approval from the National Board for Wildlife. Adani Green Energy denies any violation. A three-day show-cause notice has been issued.

· · 1 min read

Satara: All work on the Tarali pumped storage project in Patan taluka must stop immediately, the forest department has ordered. The 1,500 MW project is being built by Adani Green Energy Limited. The reason given is that work began without prior approval from the National Board for Wildlife (NBWL).

The November 13 notice was issued by R S Nalawade, forest range officer (territorial), Patan, to the project's authorised signatory. An inspection found project work under way in the Tarale area of the Patan forest range, it states.

Calling the matter "extremely serious", the notice says starting work without the approval violates the Wild Life (Protection) Act, 1972 and the Maharashtra Felling of Trees (Regulation) Act, 1964. The company has been asked to explain in writing within three days "under what authority and on what basis" it began, and to produce original or attested copies of any permission to fell trees, along with statutory clearances and maps.

Amol Satpute, deputy conservator of forests, Satara, said the action followed the department's observation that activities had begun without the mandatory approval. The notice warns of "strict legal and punitive action" if the explanation or documents do not arrive, or if work continues.

The company disputes the finding. No component of the project falls within a notified protected area and no forest land is involved, a spokesperson said, adding that a no-objection certificate confirming the absence of forest land was received on January 23, 2024, environmental clearance on February 11, 2025, and the pollution board's consent to establish on April 7, 2025. Construction began only after those approvals, the company said, and its NBWL proposal is under consideration.

The cost is the second fault line. The project was declared at Rs 5,675 crore. A notarised affidavit of September 8, 2026 cited Rs 56.75 crore, which the company says was only the survey and investigation estimate. At 4 per cent of project cost, the contribution to the Sahyadri Tiger Reserve falls from Rs 227 crore to about Rs 2.27 crore. It has deposited Rs 56.75 lakh.

Honorary wildlife warden Rohan Bhate complained on October 30, and on November 6 the Union environment ministry asked the state to investigate on priority. The project is proposed over about 150.74 hectares in Nivade, Tondoshi, Kalambe and Jalu villages.