14 more structures on the Godavari flood line, Nashik civic body tells Bombay HC

A fresh survey found 14 additional unauthorised structures in Godavari flood-line restricted areas, the Nashik Municipal Corporation has told the Bombay High Court, with notices now issued in 24 cases in all.

· · 1 min read

Nashik: A fresh survey has found 14 additional unauthorised structures in areas subject to Godavari flood-line restrictions, the Nashik Municipal Corporation has told the Bombay High Court. Notices have now been issued in 24 cases in all.

The affidavit was filed in contempt proceedings arising from public interest litigation No. 176 of 2012, and follows the high court's November 5 order directing the NMC to place on record the facts relating to allegations of illegal construction along the Godavari. Municipal commissioner Manisha Khatri affirmed it on November 19.

The civic body also defended two structures it has built on the river: the ₹17.4-crore pneumatically operated automated mechanical gate installed downstream of the Ahilyadevi Holkar Bridge, and the RCC retaining wall built as part of the Godavari beautification and riverbank protection project.

According to the NMC, the gate regulates water flow and flood levels, controls silt accumulation and maintains water levels, protecting areas including Gharpure Ghat, Ramwadi and Gangawadi from flooding. It replaced an 88-year-old stone masonry weir that the civic body says had become structurally unsafe and caused heavy silt accumulation upstream.

On the retaining wall, the NMC said it prevents soil erosion, stabilises the riverbank and protects roads, control rooms and residential areas. The earlier gabion wall was dilapidated, and the new structure came up next to the old wall, 10-15 feet away and outside the riverbed, it said.

The NMC argued that a no-objection certificate from the water resources department was not required under a May 3, 2018 government circular for works considered necessary in public interest, and that the project complied with floodplain-management guidelines and NEERI's recommendations.

It denied any deliberate breach of court orders and sought dismissal of the contempt petition. The allegations remain allegations. The court has not ruled.