163 hectares of forest for a 1,500 MW battery in the hills: Melghat project clears a hurdle

A proposed 1,500 MW pumped storage project at Adnadi in Chikhaldara taluka of Amravati district needs 240.61 hectares, of which 163.77 hectares is forest land. The project, by Adani Hydro Energy Ten Ltd, has come before the Environment Ministry's expert appraisal committee. Environmentalists have raised concern.

· · 1 min read

Amravati: A pumped storage project proposed at Adnadi in Chikhaldara taluka, in the Melghat hills, will need 240.61 hectares of land. Of that, 163.77 hectares is forest. The rest, 76.84 hectares, is non-forest land.

The proposal, by Adani Hydro Energy Ten Ltd, has come before the expert appraisal committee of the Union Ministry of Environment, Forest and Climate Change.

The Adnadi project is a closed-loop pumped storage scheme with 1,500 MW of capacity: four units of 300 MW and two of 150 MW, with storage of 9,000 MWh. Six reversible pump turbines will be installed, so that water is lifted when demand is low and released to generate when it rises.

Two new reservoirs are planned. The upper reservoir sits near Kamapur village on a non-perennial nallah, and the lower reservoir near Adnadi village on another non-perennial stream. Natural inflows are not enough to fill them, so initial filling and annual recoupment of evaporation losses will come from outside sources. The two options identified are the Sapan dam reservoir, about 4.5 km away with gross storage of 39.26 MCM, and the Chandrabhaga dam, about 5 km away with 41.4 MCM.

The committee is understood to have asked for a detailed plan for the upper reservoir, prepared in consultation with a reputed institution.

Melghat is a forest-rich and environmentally sensitive tract, and the loss of tree cover is the point local organisations have objected to. The next stage of clearances will test how that objection is answered.

The land figures are what any public hearing in Chikhaldara will now turn on: 163.77 hectares of forest against 1,500 MW of grid storage.